Bearing in mind the need for Ukraine to implement the National Plan to reduce emissions from large combustion plants, plus the difficulty for thermal general companies to keep about 12 GW of necessary capacity at thermal power plants in operation to cover peak and half-peak loads for a balanced power system, Ukraine now needs to look at constructing 5 to 6 new environmentally friendly coal-fired power units.
Fire safety is among Donbasenergo's top priorities. The yearly UAH 5 million is allotted by the energy company to improve fire safety.
Donbasenergo reports that Power Unit 7 of Sloviansk TPP was connected to the unified energy system of Ukraine on April 15, 2021 at 10:23 am.
The implementation of the National Emissions Reduction Plan for Large Combustion Plants (NERP) must urgently be brought before the National Security and Defence Council (NSDC) in order to avoid conflicts of interest between the Ministry of Environmental Protection and Natural Resources and the Ministry of Energy and Coal Industry.
As Oleh Larionov, Donbasenergo's Commercial Director, told EnergyClub, "Donbasenergo has long been and continues to be a socially conscious enterprise." Donbasenergo paid over UAH 1 billion of taxes and other obligatory payments to the state and local budgets due in 2020. Compared to 2019, the payouts are up 36%.
Donbasenergo announces that on April 9, 2021, startup and commissioning works at Sloviansk TPP, i.e. the final stage of the comprehensive overhaul of TPP's Power Unit 7, are to begin.
"Ukraine will not be able to give up coal-fired power plants in the next 20-30 years," Oleh Larionov, Donbasenergo's Commercial Director, said in an interview with EnergyClub.
Donbasenergo's Commercial Director Oleh Larionov holds firm that the key concern for electricity producers is distorted pricing in the market, causing major losses for companies.
Ivan Plachkov, chairman of the All-Ukrainian Energy Assembly, said after his field visit to Sloviansk TPP: "Thermal power generation in Ukraine is a vital component of the country's energy security and social protection for tens of thousands of people: power engineers, their family members and residents of satellite towns. This is why the state must create favourable conditions for its growth."
On March 23, 2021, Oleh Larionov, PJSC Donbasenergo's Commercial Director, spoke at the Energy Freedom talk show discussing the systemic issues of the energy market and suggesting practical ways to make it more stable.
PJSC Donbasenergo made a net profit of UAH 29.09 million in 2020 vs. the net loss of UAH 69.99 million in 2019. These figures are stated in the announcement of the annual meeting of shareholders scheduled to take place on April 26, 2021 at: 34-A Predslavynska Str., Kyiv.
The Children's Football Championship in Kyiv has come to an end. Donbasenergo and other sponsors helped make it happen.
Our company has always been and continues to be eager to support young talents, as well as sports events and teams on a regular basis.
Donbasenergo reports that the reason why the vibration of the turbine of Power Unit 7 at Sloviansk TPP increased on January 17 this year was the breakage of a fragment of the blade lock packet of working blades No. 11 of the high pressure cylinder (HPC) caused by erosion and abrasive wear of the blades in the area where they intersect with the bandage flange, since this area has a voltage concentrator.
PJSC Donbassenergo suggests postponing the deadline for measures under the National Emission Reduction Plan for large combustion plants since there is no funding program for ecological modernization of thermal power plants; it needs to be developed amid the new electricity market terms. Oleg Larionov, Commercial Director of Donbasenergo, said this in his interview with ExPro agency.
In 2020, PJSC Donbasenergo's expenses for occupational safety, fire safety and civil protection totaled UAH 50,238.6 thousand (vs UAH 17,245.8 thousand in 2019), including UAH 44,226.9 thousand for occupational safety, which is 6.1% of the payroll in 2019.
PJSC Donbasenergo abandoned the contracted supplies of domestic gas coal (grade G) in favor of the state-owned energy company Centrenergo due to the repairs in Power Unit 7 of Sloviansk TPP lasting about 65 days.
The Board of PJSC Donbasenergo notifies you that the main equipment failure occurred at Power Unit 7 of Sloviansk TPP on January 17, 2021. It happened as a result of the increased vibration of the first bearing of the turbine unit; this led to an emergency shutdown of the power unit from the Ukrainian power grid.
PJSC Donbasenergo channeled UAH 1.05 billion of taxes and other mandatory commitments to the state and local budgets, which is UAH 278.8 million or 36% higher than 2019 figures.
PJSC Donbasenergo reports that the power generation at Sloviansk TPP reached 324,873 thousand kWh in December 2020. A total of 3,089,978 thousand kWh in the 12 months of 2020.
As we approach the New Year and Christmas holidays, we would like to extend our sincere congratulations and best wishes for peace, health, prosperity, and happiness to you. We wish that these most awaited holidays of the year be the start of positive things to come!