On 15-16 December, Slavianskaya TPP of Donbassenergo hosted a field meeting of the Ministry of Energy and Coal Industry of Ukraine devoted to the performance of the industry following the results of 11 months of 2016. One of the key issues of the meeting was related to ensuring a reliable power supply. As part of the discussion, solutions for reconstruction of the outdoor switchgear (OSG) of various voltage classes developed by experts of Teploelektroproekt for Slavianskaya TPP were presented.
Presenting the project "Electricity output in the reconstruction of power unit no.6 of Slavianskaya TPP with the division into power generating units no.6b and 6a, 330 MW each", Mr Valeriy Kuleba, the deputy Technical Director of Donbassenergo voiced three possible modernization options for 330, 220 and 110 kV OSGs. Each of them, in addition to the installation of modern equipment, provides for the possibility to connect future power units of SlavTPP: power unit no.6b - to field no.5 of 330 kV OSG, power unit no.6a unit - to newly designed cell of 110 kV outdoor switchgear.
The possibility to implement the proposed solutions has been confirmed by the findings of experts from Ukrenergosetproekt NII (design institute): additional checking calculations taking into account the electrical network configuration changes (due to disconnection of some overhead lines of Donbassenergo's power system) have shown that the power output by Slavianskaya TPP when commissioning power units no.6b and 6a, as well as the regime parameters by "voltage" criterion in the area of the plant's location will be met without any limitations both in winter and in summer periods.