Unit No. 7 of Slaviansk TPP
Increase

in power efficiency and available capacity

FORECASTED COST

1 908.4 million UAH

PROJECT IMPLEMENTATION PERIOD

2013-2021

PURPOSE OF THE PROJECT

Increase in power efficiency and available capacity to 800 MW (an increase by 40 MW). Reducing dust emissions to 50 mg/Nm3 in order to improve the ecological situation in the region

Implementation of the project will also allow:


  • to improve power efficiency in maneuvering mode (increase in load range to 280-800 MW);
  • to reduce the specific fuel consumption from 411.7 to 366.08 goe / kW • h;
  • to increase electricity supply to 726 million kW • h / year;
  • to perform ENTSO-E requirements for primary and secondary regulation of frequency and power;
  • to extend the life of power equipment for 15 years.
purpose
reconstruction
SCOPE OF
RECONSTRUCTION
  • Phase I: Reconstruction of the housing of 7A boiler and auxiliary equipment, construction of tubular collector 7A, first system of PPV pulverization.
  • Completed

  • Phase II: reconstruction of the housing of 7B boiler and auxiliary equipment, construction of tubular collector 7B, second system of PPV pulverization.
  • Completed. Part of the work moved to the phase III

  • Phase III: modernization of the turbine, including the control system and condenser ball cleaning, generator, transformer, third system of PPV pulverization.
  • Completed works
    100%
    Phase I
    100%
    Phase ІІ
    30%
    Phase ІІІ